Liquids Terminal

The group, through its Quantum Oil Terminals subsidiary, is presently constructing a liquids storage and loading terminal in Tema. This project is being executed in two phases;

 

Phase One of this facility will be completed and opened in 2017 with a 30,000 MT Gasoil and 25,000MT Gasoline storage capacity. With an initial storage capacity of 55,000 MT, the facility will also be able to hold up to 50 trucks a time and have the capacity of loading out 15,000,000 litres of products daily, from its 16-truck loading bays

 

Phase Two of the project will add a further 45,000 MT to the capacity.

 

Our excellent location in the Port City makes this facility ideally placed to receive most tanker sizes and also undertake regional distributions. Total Cost of the Facility is about USD53 million

 

Early Power

We are co-developers and equity partners in the 400MW Early...

Gas Terminal

We are in the process of constructing a gas storage...